User : Not Logged In
Call Us On :
UK: 0800 310 1040
Ireland: 353 74 9561500
  Your IP Address : 38.107.191.117
 
   
     
31 July 2010
       
    or Register
       
  HOME
  SEARCH NOTICES
  CURRENT DOCUMENTS
  AUTHORITY SECTION
  PROCUREMENT GUIDE
  CONTACT US
  LATEST NEWS
  LINKS
  HELP
  PRIVACY POLICY
  TERMS & CONDITIONS
       
       
       
 
Guide to Tendering
       
 


Guide to Tendering

How do I tender

Qualifying for tenders

Awarding tenders

Tendering Tips

Advertising your own procurement needs



Guide to tendering

The public procurement directives are based on three main principles:
  • Community-wide advertising of contracts so that all firms in all member states have an opportunity of bidding for them
  • The banning of any technical specifications liable to discriminate against potential foreign bidders
  • Application of objective criteria in tendering and award procedures
The latter principle is ensured by the following requirements:
  1. Types of Procedure
    The Directives provide for three types of procedure that contracting authorities can use:
    • Open procedure
      All interested suppliers, contractors or service providers may submit tenders.
    • Restricted procedure
      Only those suppliers, contractors or service providers invited by the contracting authority may submit tenders
    • Negotiated procedure
      The contracting authority consults suppliers, contractors or service providers of its choice and negotiates the terms of the contract with one or more of them.
      Note: The negotiated procedure may be used only in justified cases and if the conditions required for its use are fulfilled.
      For (Utilities) contracts they have a free choice between all three procedures provided that a call for competition notice has been published in the Official Journal.
      It should be stressed that in open and restricted procedures, all negotiation with candidates or tenderers on fundamental aspects of contracts, and in particular on prices, is ruled out; however, discussions with candidates or tenderers may be held, but solely for the purpose of clarifying or supplementing the content of their tenders, or the requirements of the contracting authorities and provided this does not involve discrimination.
    Back to top

  2. Contract Types
    Four different types of contract are identified in EU Directives:
    • Works contracts- buildings and civil engineering works
    • Supplies contracts- purchasing goods and supplies
    • Services contracts- advertising, property management services, architectural / engineering / surveying, management consultancy services and so on.
    • Combined contracts - some tenders that are a combination of a supply and service contract or a works and service contract can be classified as a combined contract.
    Back to top

  3. Types of tender documents
    Tender documents can be classed as:
    • PINS- Prior Information Notices are published annually as an indication of the possible contracts, which may be awarded in the coming year.
    • Opportunities- Tender notices (Invitation to Tender) are aimed at specific contracts and invite suppliers to make an application to be placed on the tender list or to be provided with information.
    • Awards- Award notices contain details of which tender contracts have been awarded, the awarding criteria and the successful candidate.
    Back to top

  4. Threshold Values
    Bodies and organisations that must comply with these thresholds can be split into two distinct groups:

    General - for all Government Departments, Local and Regional Authorities.
    Special - for Public Authorities, Public undertakings and Organisations that operate on the basis of special or exclusive rights granted by a competent authority of a Member State in the water, energy, transport and telecommunications sector.

    These threshold values apply to both Tendering Opportunities and PINS.

    Tenders
    • Services and Supplies - *General - €200,000 (Directives 92/50 & 93/36) *Where the above threshold is reached by having separate contracts for different lots for Services, then any lot over €80,000 and not exceeding 20% of the total value of all the lots, becomes the threshold.
    • Services and Supplies - Special (*Utilities) - €400,000 (Directive93/38) *The provision or operation of fixed networks for drinking water, electricity or gas (heat); oil/gas exploration and extraction, provision of airports; maritime or other inland ports; public transport.
    • Services and Supplies - Special (*Telecommunications) - €600,000 (Directive93/38) *The provision or operation of public telecommunications networks.
    • Works - *€5,000,000 - General (Directive 93/37), Special (93/38) *Where the above threshold is reached by having separate contracts for different lots, then any lot over €1,000,000 is the threshold. Any lot below this is exempt provided it does not exceed 20% of the total value of all the lots.

    Periodic Information Notices (PINS) - €750,000
    Applicable to all Services and Supplies contracts (Directive 92/50; 93/36; 93/38)

    Contracts below the various thresholds may also be covered by the Directives. Thresholds exclude VAT
    Back to top

  5. European Directives
    All Government Departments, Local and Regional Authorities, non-commercial State Bodies and organisations dependent on the State for more than 50% of their funding are subject to the Directives. There is a separate regime for the utilities - water, energy, transport and telecommunications.
    • The Works Directive in force is 93/37/EEC (OJ L 199/54 of 9.7.1993) consolidating Directives 71/305/EEC and 89/440/EEC.
    • The Supplies Directive in force is 93/36/EEC (OJ L 199/1 of 9.7.1993) consolidating Directives 88/295/EEC, 80/767/EEC and 77/62/EEC.
    • The Services Directive in force is 92/50/EEC (OJ L 209/1 of 24.7.1992)
    • The Utilities Directive in force is Council Directive 93/38/EEC (14.06.1993)
    Back to top


How do I tender

  1. Using the CPV Code
    The CPV (Common Procurement Vocabulary) Code was developed to promote ease and transparency in the public procurement arena. By using a standard method of classification codes potential suppliers can identify the contracts that are of interest to them.
    The CPV is an 8-digit code. Awarding authorities may often use more than 1 code to accurately describe a particular opportunity. The codes may be used broadly to describe the industry sector of more narrowly to define a particular product or service, e.g.:

    For example, if we take a tender for the construction of a road bridge, the diagram above shows the different steps through the CPV code starting at the highest level:
    45000000 - Construction work
    And ending at the lowest level
    45221111 - Road Bridge.
    Back to top

  2. How do I get more information on a specific opportunity
    Most notices contain contact details of the Awarding Authority. In the case of Award notices it will contain details of the successful applicant. Notices usually contain an address field with details of where to obtain further details.
    Alternatively simply contact us quoting the Document Number and we will obtain further details on your behalf.
    Back to top

  3. Replying to tenders and getting on tender lists
    Once you have identified a tendering opportunity that is of interest to you and obtained information on the awarding authority, the next step is to reply to the tender and get yourself on the tendering list. The best way to ensure inclusion onto a tendering list is to:
    • Ensure you supply all the information required as set out in the tender notice by the awarding authority.
    • Convince the awarding authority that your products / services meet the necessary performance criteria and specifications
    • Convince the awarding authority that your company meets all the criteria for inclusion on tender lists
    • Respond promptly to any requests for information or clarification arising from your application.
    Back to top

  4. Timescales for replying
    The normal periods that contracting authorities must allow for receipt of tenders is no less than 52 days for an open procedure and no less than 40 days for a restricted procedure.
    This may be reduced to 36 and 26 days respectively, in the cases of works or service contracts where an indicative notice has been published.
    Back to top

  5. Tendering checklist
    • Do you have the necessary resources?
    • Does your product/service meet the specifications set out in the tender document?
    • Can you meet the delivery schedule?
    • Can you meet the closing date and time for receipt of tenders?
    • Can you tender for part of the contract or must you tender for everything?
    • Do they require financial information on your company?
    • Do they want details and references of previous contracts?
    • Do they want details of your personnel and qualifications?
    • Do they want details of your plant and any specialized equipment?
    • Will you be able to provide a Tax Clearance Certificate, if successful?
    Back to top


Qualifying for tenders

  1. What do I need to apply
    Awarding authorities look for similar information when evaluating potential suppliers for tender lists. The requirements may vary in detail and structure depending on the nature of the tender, but the vast majority look for information to assess the skills, efficiency, experience and reliability of the potential suppliers. This information usually takes the form of:
    • Financial and Economic Information
    • Information Supporting Technical Capacity
    Back to top

    Financial and Economic Information that may be required
    • Balance Sheet Information
    • Bank Statements
    • Turnover over the previous 3 financial years
    • Evidence of overall turnover and turnover in respect of services/products to which the contract relates, over the previous 3 financial years
    • Any document which the Public Sector Organisation considers appropriate
    • Relevant professional risk indemnity insurance
    Back to top

    Information Supporting Technical Capacity that may be required
    • A list of principal product deliveries/services provided over the previous 3 years with details of amounts, dates and recipients (whether in the public or private domain).
    • The technical bodies and personnel responsible for monitoring your quality control and conformance with other standards.
    • Recognised third party certification of conformity of the products/services to given specifications and industry standards.
    • For complex or special purpose services/products, a possible check on the supplier's/service providers technical ability, study and research facilities or quality control measures carried out by an official body in the supplier's country of establishment.
    • Information on Health and Safety aspects
    • Information on Environmental Controls
    • The educational and professional qualifications of managerial staff and of those responsible for providing the services.
    • Average annual manpower and the number of managerial staff for the last 3 years.
    • The tools, plant or equipment available for the carrying out of the services.
    • An indication of the proportion, if any, of the contract, which the service provider intends to sub-contract
    • Quality assurance standards referring to EN29000 European Standards series. (see ISO9000)
    Back to top

  2. Qualification criteria
    Qualification criteria must be clearly laid out either in the notice, or the tender documents, preferably in order of importance. They must be easily identifiable - it is not acceptable for potential tenderers to have to interpret documentation in order to establish the criteria as this may lead to inequality due to alternative interpretation.
    Back to top



Awarding tenders

  1. European criteria for awarding tenders
    Awarding Authorities when deciding which bid to accept may do so on the basis of either:
    • The lowest price only
    • The most economically advantageous tender - using various criteria such as price, period for completion, running costs, profitability, technical merit.

    If an Awarding Authority chooses to use the "most economically advantageous" method, this must be stated in the tender notice or documents. Details must include which criteria it intends to apply to the award, and their order of importance.
    Back to top

  2. Who won what tenders and why
    Details of any contract awarded must be notified to the Commission no later than 48 days after the award of a particular contract. Award notices should include information on the successful tenderer as well as the awarding criteria.
    Back to top

  3. Why didn't I win that tender
    Tenderers should be informed without undue delay if they have been unsuccessful. Awarding Authorities must release the relevant information to unsuccessful tenderers who inquire as to why their bids were not accepted.
    Back to top


Tendering tips

  • You do not have to be established in any particular location as long as you have the ability to meet the response times of the buyer
  • If you have tendered a particular buyer recently, you should not have to re-supply information, which you have previously made available to the buyer
  • There is no need for a permit issued by a government department or to be on an "official list" in order to apply for a contract. However, this is not to be confused with tender lists, which the public sector commonly use when seeking product/service providers.
  • The resources of other suppliers may be availed of while tendering as long as you supply proof of a relationship/arrangement between you and the other supplier.
  • Tender details must not mention products/services of a specific make, source, process or trademark. However, if it is absolutely essential to describe something by these terms, the words "or equivalent" must be used.
  • You will not be permitted to sub-contract an entire contract to another supplier.
    Back to top



Advertising your own procurement needs

  1. Advertising in the OJEC
    Only government bodies and certain qualifying private companies (government strategic interest companies such as transport, utilities, energy and telecommunications) are allowed to advertise on the OJEC. Notices for the Official Journal should be drawn up in accordance with the relevant directives. Advertising in the OJEC is free of charge.
    Back to top

  2. Advertising on this site
    Coming Soon........
    Back to top